Material Linked Invoice Items

In cases where a User wants to convert an Estimate into an Invoice, Materials may be linked to Company Invoice Items.

To link a Company Invoice Item to a Material, click the green circle plus, pick a Company, and pick an Invoice Item. Repeat for all Companies that require this functionality.


Example

The Estimate below shows the above Material being used.


Add an invoice and import items.


On the Active estimates tab, pick the estimate in the Estimates by line section (below Estimates by total).

Import Invoice Items, Active estimates tab.


The correct invoice items should now be shown. Any unlinked materials will default to the default Company Invoice Item.

The invoice after Estimates by line: each estimate line is now an invoice item.

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.